Case study
City Beach: 3-phase switchboard upgrade and EV charger install
An extremely messy old switchboard containing asbestos, replaced with a new labelled 3-phase board, then a customer-supplied 3-phase EV charger installed on a two-storey home with a raked ceiling.
What the customer needed
A 3-phase EV charger, supplied by the customer, at a home whose switchboard had no room for it.
Site constraints
The old switchboard was extremely messy, contained asbestos and had no room for the EV charger circuit. The home is two storeys with a raked ceiling, which made getting the new cable across to the switchboard a real challenge.
What we did
We completed a 3-phase switchboard upgrade: a new Clipsal board with safety switch protection on every circuit, every circuit clearly labelled, and the wiring tidied up and made compliant. We then installed a new dedicated 3-phase 32A circuit with 3-phase RCBO protection, ran 5-core cable from the switchboard to a 40A 3-phase isolator, and mounted and connected the customer’s 3-phase EV charger. The raked ceiling made the cable run difficult, but we made it happen.
The result
A safe, modern, clearly labelled switchboard, and a 3-phase EV charger ready to use.