Case study
Landsdale: three phase myenergi zappi EV charger so staff can charge at work
A Landsdale business wanted its staff to be able to charge their electric cars at work. We installed a three phase myenergi zappi in the warehouse, on its own protected circuit.
What the customer needed
A Landsdale business wanted an EV charger at its premises so staff could charge their cars while at work.
Site constraints
The charger had to go on a concrete panel wall inside the warehouse, beside the existing switchboard.
What we did
We installed a myenergi zappi three phase tethered charger on the concrete panel wall in the warehouse. It runs on a new three phase 32A circuit, with a three phase 32A RCD in its own enclosure next to the existing switchboard, cabled to a 40A three phase isolator at the charger.
The result
Staff can plug in and charge at work, on a dedicated, protected circuit.