Case study
Mount Helena: switchboard upgrade and three Mitsubishi Heavy Industries split systems
An old fuse board replaced with a new Clipsal Resimax switchboard with RCBOs, an old split system swapped for an 8kW Bronte, and two new split systems added in a Mount Helena home.
What the customer needed
The owners of a Mount Helena home wanted to replace an old split system and add heating and cooling to two more rooms. The switchboard still had old ceramic fuses, so it needed upgrading too.
Site constraints
There was no roof cavity to run new power for one of the systems, so we used an existing circuit the owners had in place. Each system was installed back to back, with the indoor and outdoor units on the same wall.
What we did
We replaced the old switchboard with a new Clipsal Resimax board, swapping the ceramic fuses for circuit breakers with RCD protection on every final sub-circuit, checking the main earth, fire sealing the board and labelling every circuit. We removed and disposed of the old split system and replaced it with an 8kW Mitsubishi Heavy Industries Bronte, with all the old copper pipe replaced with new. We then installed a second 8kW Bronte on an existing dedicated circuit, and a 3.5kW Mitsubishi Heavy Industries Ciara Series system with Wi-Fi. Each outdoor unit sits on the ground on air-con feet, with the pipework run in duct cover.
The result
A safe, clearly labelled switchboard with RCD protection on every circuit, and heating and cooling in three rooms.